Publishing TFS in the cloud - version-control

I've been testing TFS in the cloud, and have it all set up with a test project. Not using Git currently. My question is related to publishing to our remote server. I have a drive mapped and connect over VPN, and publishing via file system works. It appears that publishing occurs from my local solution, and not the solution in the central repository. This allows files that are checked out to be published to production. I had thought publishing would occur from the central repository, and only publish the files that are checked in.
Is the publishing process supposed to move the files from the central repo? Or, am I doing something wrong?
If not, are there controls in TFS to only publish approved/tested production files, and only files that are checked in? For example, prevent publishing and notify developer if files are checked out.
It's been a long time since I've used SCM, so bear with me. Thanks for your patience.

I think you need to investigate the build service built into TFS as this will let you generate builds using only the checked in source. A guide to doing this using the TFS cloud can be found here.

Related

Is There A Way To Backup Visual Studio Team Services Projects?

I'm advocating using Visual Studio Team Services for our source control solution, and have actually started doing so. However, my manager, who is somewhat apprehensive when it comes to cloud-hosted storage and services, wants to know what our contingency plan is in the event of Team Services ceasing to be accessible for whatever reason.
I've pointed out that we have our source code on our developers' computers, in their mapped work spaces, but admittedly if we ended up with just that and no access to Team Services we'd certainly be in a bit of bind. They might all be working on different parts of the same solution and we wouldn't be able to check all of their changes back into the central repository or merge changes made in separate branches. We also wouldn't have access to the comments associated with previous check-ins, or our backlog, tests, etc.
So, the question is, is there a way to backup everything that we're hosting in Team Services so that, in the event of something going wrong, we'd be able to restore all of that to a locally-hosted installation of TFS (or somewhere else)?
I'm a bit late to the party but we developed a Team Services backup tool. We scheduled it as a scheduled task and it runs once a night. It then just clones all our repositories to disk.
Taken from this blog:
We use the VSO Rest API to query our VSO account and get all the data
we need. Since in VSO you can only have one Team Project Collection,
we retrieve all the team projects of the default collection. Each of
these team projects can have multiple repositories that need to be
backed up. A folder is created for each team project and saved to a
location on disk that can be configured in the app.config. When the
team project folder is created, the task loops over each repository in
the team project and creates folders for each repository.
You can also fork it on GitHub here
There's no out of the box backup ability.
Now, if you are only referring to source control, and not work items, pull requests, builds, test plans or anything else that the service offers, then I'd suggest you migrate your code over to git.
With git every developer will have a complete copy of the source repository, including all history and commit comments. From there, it's a simple task to push the git repository to a different git hoster (such as bitbucket or github) and make them your new centrally hosted git repository.
On a historical note, Visual Studio Team Services at one point offered a data export for a period of time. You might want to add a vote or three to this related UserVoice idea to help raise the importance of the feature with Microsoft.
Side comment: The business risks in using Visual Studio Team Services will come from either Microsoft shutting down the Visual Studio Team Services service or that the underlying Azure infrastructure has such a catastrophic failure that your Visual Studio Team Services account is unrecoverable. Both of those are extremely low risk, and very likely lower than the risks you'd have running TFS on-premises, in your own data centre, unless of course, your infrastructure and staff are better than Microsoft's :-)
Not a full VS backup in terms of a restore of service. But you can take a full Zip from root down using the Code web site. Right click the root folder and has a zip download option. Pretty neat feature.
The easiest way to back up everything is to use something like the TFS Integration Platform to periodically pull off all your data into an on-premises TFS solution. I've set this up using an Azure VM that we turned off when we weren't actively backing up, which makes it really low cost. For more info on using the TFS IP with Team Services, see this: http://nakedalm.com/migration-from-tf-service-to-tf-server-with-the-tfs-integration-platform/

is there a deploy tool (or set of tools) that supports rollback of a deployment?

I'm learning FluentMigrator. The thing that I like about FM is that it supports the idea of Forward and Back for migrations (aka Up/Down). I'm finding that it's not ideal about this; there are some holes. Still, it's good.
This leads me to wonder if there are any deployment tools (nant, msbuild or other) that support this idea of rolling forward and back. The scenario that I'm using it in is the deployment of a web app with a related database.
Ideally I'd like to set up my deployment so that, should any part of it fail, it will revert to the previous known working configuration. With FM, this is pretty easy to do (but there are rough spots), so that covers the db. How about the files that make up the web app? Do any deploy tools have support for this?
Deploying to a Windows Server. Assume that I can't make any changes to the server.
I don't know of any Microsoft-centric, automated provisioning/deployment tools like Capistrano. Here are some tools I've heard of, but never used:
MSDeploy, for deploying web application.
Microsoft Deployment Services, for managing operating system configuration
Microsoft's System Center Configuration Manager
BladeLogic
HP's Operations Center
Up until about three months ago, we did our deployment/provisioning using custom MSBuild scripts. After a server is provisioned, deploys happen automatically using Robocopy to copy files to a share on the application server, updating changed application binaries and markup files. We've never had a need to rollback any of our deployments, but since our scripts are custom, we could write the logic if we needed to.
MSBuild is a terrible deployment/provisioning language. For the past three months, we've been writing all new scripts in, and porting existing ones to, PowerShell. It is wonderful. With version 2, there is support for running commands on remote servers, like SSH. We haven't used that functionality yet, but I'm looking forward to pushing setup scripts to remote server to provision and deploy at the same time.
We have been using Git to do our deploys for the last 6 months.
Here is the whole process:
CI server build the project
CI server checks it in to a local git repository
CI server pushes the changes to the centralised git repository
User creates an empty repository on the live server
User adds the central git repository to the remotes
User pulls the latest version over https (no need to open any ports)
It is a lot to setup in the beginning but once setup it works great. Deploys take seconds as only changed files get copied.
Another great thing about this method is that git keeps history of changes so rolling back is pretty simple. You can also roll back a few revisions and it's done straight on the live server. If something goes wrong reverting is super fast.
Also you can save some time if you use a hosted git service (github) for your central repository.
This is a very brief description but I can give you more info if you want.
Of course! My favorite is Capistrano. This was originally built for Ruby but I've found that it works just as well for other languages.
https://github.com/capistrano/capistrano

What is a typical workflow to put my local MVC3 project on to a "live server"?

I develop on my local machine with VS2010 and SQL Server. Naturally, my web.config points to my local SQL Server and I can debug/development and all is well. Unfortunately, I am not entirely sure on how to go about deploying my code to a live server.
Currently, my live server consists of a virtual machine (my site is accessible from the internet). When I'm ready to put my changes on the live server I publish my app (right click on solution explorer -> publish). Then I go to the directory it publishes to and dump all the files into a network share that goes to my site on the live server. On the initial copy over, I have to manually edit the web.config so that the connection string points to the SQL Server on the live server instead of my local machine. So this is my first stumbling block. How can I easily manage development settings and "live" settings in the web.config?
Now, I also use version control (Kiln). Can I possibly tag a changeset and have it automatically deployed to my live server somehow? Let's say someone submits a bug and I fix it. I push my changeset and now Kiln has the latest version of my code with the bug fix. What's the best way to get these changes on to a live server?
I'm unable to find any documentation that covers the entire workflow but I feel like there has go to be a better way. Surely, something like this can be accomplished without having to manually edit the web.config everytime I publish and pray to the computer Gods that I didn't miss something in the connection string.
It's just me so I have complete control over all of my environments, including the server and what's accessible via the internet, and anything is possible if only I knew what to do.
How can I easily manage development settings and "live" settings in the web.config?
Re: With VS 2010 web.config transformations, it is quite easy. Please take a look at this blog:
http://blogs.msdn.com/b/webdevtools/archive/2009/05/04/web-deployment-web-config-transformation.aspx
For VS 2008 or older, we used to have multiple config file based on environment and we used to create Debug/Release/DevTest/UAT/PROD release configuration and then in the post build event we used to replace the web.config with the release configuration based config. For example - if you build the project using "Prod" release configuration then we copy the PROD web.config to the publishing folder.
Now, I also use version control (Kiln).
Can I possibly tag a changeset and have it automatically deployed to my live server somehow? Let's say someone submits a bug and I fix it. I push my changeset and now Kiln has the latest version of my code with the bug fix. What's the best way to get these changes on to a live server?
Re: Source control and publishing to live server are two different things. The first question you are asking here related to how you manage multiple releases and have control over bug fixes for each release. The way I would do it is I will have PROD branch in my source control which will be the first release and for every major release I will sub branch it to have more control over e-fixes.
For the other question about how to get it to live server, it depends on your environment. We do it differently based on how customer environment is setup. If they have given us the FTP, we use that or otherwise we package the application into an MSI and then deploy it to UAT.. Until UAT signoff is done, we keep on updating the MSI. Once signoff received, the MSI goes to PROD.
Hope this helps.

Organizing workflow with Mercurial and Netbeans (+ bitbucket.org?)

I've never worked with any version control systems before. Now I'm trying to learn Mercurial, but I'm confused (I've already read about 10-15 articles + hginit.com). I don't know how to organize the workflow.
I have a testing server and a production server. I work from my office computer and from my home laptop. I make changes directly on the testing server, and every week or so copy new code to my production server. I also need wiki/issues/etc. pretty much everything bitbucket.org has. I know that's a bad way of doing things.
Is there any tutorial or articles on how to organize the workflow? I'd also appreciate any schemes/sketches describing the process.
Thank you!
[Edit: Changed based on comments]
Using Bitbucket
Once you have created an account.
You should be able to create a repo with an appropriate url. Then you can clone it to create a local repository.
Check out getting started.
See the following to push the updates to BitBucket.
BitBucket comes with very extensive documentation.
Also there are, other useful tools to work with BitBucket:
BitbucketExtension that allows you to use command line for a number of operations.
Using Mercurial Queues and bitbucket.org
Organizing workflow
You will have to evolve a workflow that suits you. In your case, it looks like you have a testing server and production server.
So , you can setup two repositories, one for the testing server ad one for production. You can make push to testing server automatic so that you can test out the changes immediately. You can tag releases that are then pushed to production server.
Your local repo can be used to publish changes to testing server.
You can push the approved changes, tagged to BitBucket repository.

Eclipse / Aptana File Sync Solutions

Our development team uses Eclipse + Aptana to do their web development work. Currently, most of them are mapping their Eclipse projects directly to the web server. I'd rather them create a local project and use that to sync to the web server project directory they are working on.
The issue is that there aren't any good solutions which is just appalling given the popularity of the two.
The FileSync plugin for Eclipse is only one-way. Meaning if another developer makes a change to the file on the server, another dev isn't even notified and could overwrite the change.
The File Transfer option in Aptana 2.0 doesn't support any sort of Sync, just manually uploading/downloading files.
The Sync option in Aptana 1.5.1 doesn't allow you to merge files when they are different. You can only update one or the other. It does however allow you to view a diff (but only if you right click and select) and in that diff you can't make any changes.
I did find a way to allow files to be uploaded to their Sync repositories in Aptana using Eclipse Monkey. However it doesn't work if a user saves multiple files at once, 'Save All', again it doesn't work. And additionally, there is no notification if a user opens a local file that has an updated copy on the server. I tried to add one using Eclipse Monkey but I couldn't find any sort of listener in the Eclipse API to do it and any Eclipse Monkey documentation is far and few between.
My only solution at this point is just to let them continue to map directly to the server or ask them to do a manual download before they do any work (but again what if someone uploads a change right after they do that).
Anyone have any ideas?
April 2010
Add EGit to your Eclipse+Aptana setup, and:
let developers push to a local bare repo their developments (see also this post)
let your local project be updated by a git pull from that same local bare repo (creating/updating) a local working directory with sources merged/updated (or by using a post-update hook as described in my previous SO link)
let your local Aptana+Eclipse(+EGit) reference that local working directory, also used by your web server.
In short, when you are speaking of file synchronization + merges, this is a job for a (D)VCS (Version Control System: Centralized or Distributed VCS)
Oct 2011: as xmedeko mentions in the comments, Aptana3 has its own Git plugin.
And it isn't very compatible with EGit: See bug 1988.
Adding to VonC answer (which is correct IMHO), what probably lies beneath this scenario is that the process you adopted is not correct in itself, apart from the tools used.
If I understood well, you should not allow nor perform a direct upload from a development version of the project to the web server. Merging is not a job for remote synchronization tools, and it should happen well before the deployment phase (upload to web server is practically a deploy).
You should have a dedicated repository taken from some point in development history (according to you release timeline), a point where merge has already happened. Then deploy it (by means of file synchronization if you want, but that is not mandatory) on a local/staging web server.
Perform there any test you run on the web site actively running (i.e. integration and/or functional tests). If there's any bug & fixing, well there are different ways to actually apply the fixes on development & staging code repository. Only after that, you deploy the staging repository on to production web server (again, synchronization tools are a way to do that).