How should a Modbus device fail if an error is encountered after a Write Multiple Register (0x10) request has been validated but before all writes have been completed? The specification (6.12) seems vague on this point and web searches have not proven fruitful. I see three possibilities:
Attempt to write each register in turn. If an error occurs immediately give up/send an exception.
Treat the request as an atomic transaction where either all data should be written or none of it.
Attempt to write all data sending an exception at the end if any failure was observed.
Is there a conventional or proper way to fail here or is the way a device fails implementation specific requiring only that it be documented in the manual?

According to Figure 22: Write Multiple Registers state diagram on page 31 of the specification exception code 4 should be returned but the protocol itself does not specify how the application layer should work.
The way your device fails must consider constraints and possible side effects. For example if you accept some control commands (set point value or just setting multiple outputs assigned to different registers) it is a good practice to never assign such values directly from registers but with some validation first before re-writing the value to internal program variables which are used to drive IOs or influence any control actions. Such approach complies with option 2 from your list.
You can implement whatever behavior works best provided it’s documented. If your slave is under control of a master capable of implementing part of your application layer you may also consider support for diagnostic or error information requests from slave in case of failure but such functionality is not specified for exception 0x4 to function code 0x10.

Since master can't know what is successfully written and what is not in case of such a partially failed write operation, most appropriate approach would be "all-or-nothing", just like you mentioned at #2. It's the hardest path to implement, but it's the only approach where master won't end up in an ambiguous state on such an error.

Related

Parameter sniffing / bind peeking in PostgresSQL

The Prepare and Execute combination in PostgreSQL permit the use of bound parameters. However, Prepare does not produce a plan optimized for one set of parameter bindings that can be reused with a different set of parameters bindings. Does anybody have pointers on implementing such functionality? With this, the plan would be optimized for the given set of parameter bindings but could be reused for another set. The plan might not be efficient for the subsequent set, but if the plan cost was recomputed using the new parameter bindings, it might be found to be efficient.
Reading and using parameter binding values for cardinality estimation is called "parameter sniffing" in SQL Server and "bind peeking" in Oracle. Basically, has anybody done anything similar in PostgreSQL.
PostgreSQL uses a heuristic to decide whether to do "bind peeking". It does peeking the first 5 times (I think it is) that a prepared statement is executed, and if none of those lead to better (expected-to-be-better) plans than the generic plan was, it stops checking in the future.
Starting in v12, you can change this heuristic by setting plan_cache_mode.
Note that some drivers implement their own heuristics--just because you call the driver's prepare method doesn't mean it actually transmits this to the server as a PREPARE. It might instead stash the statement text away, wait until you execute, and then quote/escape your parameters and bundle them up with your previously pseudo-prepared statement and send them to the server in one packet. That is, they might treat the prepare/execute separation simply as a way to prevent SQL injections, not as a way to increase performance.

Lagom | Return Values from read side processor

We are using Lagom for developing our set of microservices. The trick here is that although we are using event sourcing and persisting events into cassandra but we have to store the data in one of the graph DB as well since it will be the one that will be serving most of the queries because of the use case.
As per the Lagom's documentation, all the insertion into Graph database(or any other database) has to be done in ReadSideProcecssor after the command handler persist the events into cassandra as followed by philosophy of CQRS.
Now here is the problem which we are facing. We believe that the ReadSideProcecssor is a listener which gets triggered after the events are generated and persisted. What we want is we could return the response back from the ReadSideProcecssor to the ServiceImpl. Example when a user is added to the system, the unique id generated by the graph has to be returned as one of the response headers. How that can be achieved in Lagom since the response is constructed from setCommandHandler and not the ReadSideProcessor.
Also, we need to make sure that if due to any error at graph side, the API should notify the client that the request has failed but again exceptions occuring in ReadSideProcessor are not propagated to either PersistentEntity or ServiceImpl class. How can that be achieved as well?
Any helps are much appreciated.
The read side processor is not a listener that is attached to the command - it is actually completely disconnected from the persistent entity, it may be running on a different node, at a different time, perhaps even years in the future if you add a new read side processor that first comes up to speed with all the old events in history. If the read side processor were connected synchronously to the command, then it would not be CQRS, there would not be segregation between the command and the query side.
Read side processors essentially poll the database for new events, processing them as they detect them. You can add a new read side processor at any time, and it will get all events from all of history, not just the new ones that are added, this is one of the great things about event sourcing, you don't need to anticipate all your query needs from the start, you can add them as the query need comes.
To further explain why you don't want a connection between the two - what happens if the event persist succeeds, but the update on the graph db fails? Perhaps the graph db is crashed. Does the command have to retry? Does the event have to be deleted? What happens if the node doing the update itself crashes before it has an opportunity to fix the problem? Now your read side is in an inconsistent state from your entities. Connecting them leads to inconsistency in many failure scenarios - for example, like when you update your address with a utility company, and but your bills still go to the old address, and you contact them, and they say "yes, your new address is updated in our system", but they still go to the old address - that's the sort of terrible user experience that you are signing your users up for if you try to connect your read side and write side together. Disconnecting allows Lagom to ensure consistency between the events you have emitted on the write side, and the consumption of them on the read side.
So to address your specific concerns: ID generation should be done on the write side, or, if a subsequent ID is generated on the read side, it should also provide a way of mapping the IDs on the write side to the read side ID. And as for handling errors on the read side - all validation should be done on the write side - the write side should ensure that it never emits an event that is invalid.
Now if the read side processor encounters something that is invalid, then it has two options. One option is it could fail. In many cases, this is a good option, since if something is invalid or inconsistent, then it's likely that either you have a bug or some form of corruption. What you don't want to do is continue processing as if everything is happy, since that might make the data corruption or inconsistency even worse. Instead the read side processor stops, your monitoring should then detect the error, and you can go in and work out either what the bug is or fix the corruption. Of course, there are downsides to doing this, your read side will start lagging behind the write side while it's unable to process new events. But that's also an advantage of CQRS - the write side is able to continue working, continue enforcing consistency, etc, the failure is just isolated to the read side, and only in updating the read side. Instead of your whole system going down and refusing to accept new requests due to this bug, it's isolated to just where the problem is.
The other option that the read side has is it can store the error somewhere - eg, store the event in a dead letter table, or raise some sort of trouble ticket, and then continue processing. This way, you can go and fix the event after the fact. This ensures greater availability, but does come at the risk that if that event that it failed to process was important to the processing of subsequent events, you've potentially just got yourself into a bigger mess.
Now this does introduce specific constraints on what you can and can't do, but I can't really anticipate those without specific knowledge of your use case to know how to address them. A common constraint is set validation - for example, how do you ensure that email addresses are unique to a single user in your system? Greg Young (the CQRS guy) wrote this blog post about those types of problems:
http://codebetter.com/gregyoung/2010/08/12/eventual-consistency-and-set-validation/

Is it correct to use TargetSubID as a flag for test data in FIX protocol?

We are currently working on a FIX connection, whereby data that should only be validated can be marked. It has been decided to mark this data with a specific TargetSubID. But that implies a new session.
Let's say we send the messages to the session FIX.4.4:S->T. If we then get a message that should only be validated with TargetSubID V, this implies the session FIX.4.4:S->T/V. If this Session is not configured, we get the error
Unknown session: FIX.4.4:S->T/V
and if we explicitly configure this session next to the other, there is the error
quickfix.Session – [FIX/Session] Disconnecting: Encountered END_OF_STREAM
what, as bhageera says, is that you log in with the same credentials.
(...) the counterparty I was connecting to allows only 1 connection
per user/password (i.e. session with those credentials) at a time.
I'm not a FIX expert, but I'm wondering if the TargetSubID is not just being misused here. If not, I would like to know how to do that. We develop the FIX client with camel-quickfix.
It depends a lot on what you system is like and what you want to achieve in the end.
Usually the dimensions to assess are:
maximising the flexibility
minimising the amount of additional logic required to support the testing
minimising the risk of bad things happening on accidental connection from a test to a prod environment (may happen, despite what you might think).
Speaking for myself, I would not use tags potentially involved in the sesson/routing behavior for testing unless all I need is routing features and my system reliably behaves the way I expect (probably not your case).
Instead I would consider one of these:
pick something from a user defined range (5000-9999)
use one of symbology tags (say Symbol(55)) corrupted in some reversible way (say "TEST_VOD.L" in the tag 55 instead of "VOD.L")
A tag from a custom range would give a lot of flexibility, a corrupted symbology tag would make sure a test order would bounce if sent to prod by accident.
For either solution you may potentially need a tag-based routing and transformation layer. Both are done in couple of hours in generic form if you are using something Java-based (I'd look towards javax.scripting / Nashorn).
It's up to the counterparties - sometimes Sender/TargetSubID are considered part of the unique connection, sometimes they distinguish messages on one connection.
Does your library have a configuration option to exclude the sub IDs from the connection lookups? e.g. in QuickFix you can set the SessionQualifier.

How to update regmodel with writes going from RTL blocks

I understand that regmodel values are updated as soon as transaction initiates from test environment on any of the connected interfaces.
However consider a scenario:
RTL registers being updated from ROM on boot-up (different value than default)
Processor in RTL writing to register as compared to test environment.
In these 2 cases regmodel doesn't get updated/mirrored with correct RTL value. I would like to know what is correct procedure to get regmodel updated, if there is none at the moment what other approach can be taken to keep these 2 in sync?
For the first case you have to pre-load your memory model with your ROM contents at the start of the simulation. There isn't any infrastructure to do this in uvm_memory (unfortunately), so you'll have to implement it yourself.
For the second case, you have to use a more grey-box approach to verification. You have to monitor the bus accesses that the processor does to the peripherals and update the register values based on those transactions. This should be OK to do from a maintainability point of view, because the architecture of your SoC should be pretty stable in that sense (you've already decided to use a processor so that will always be there, but you might not know which peripherals will make it to the end).

BEST approach to share messages between data tier and application tier

I was looking for any suggestion or a good approach to handle messages between the data & application tier, what i mean with this is when using store procedures or even using direct SQL statements in the application, there should be a way the data tier notifies upper layers about statement/operation results in at least an organized way.
What i commonly use is two variables in every store procedure:
#code INT,
#message VARCHAR(1024)
I put the DML statements inside a TRY CATCH block and at the end of the try block, set both variables to certain status meaning everything went ok, as you might be thinking i do the opposite on the catch block, set both variables to some failure code if needed perform some error handling.
After the TRY CATCH block i return the result using a record:
SELECT #code AS code, #message AS message
These two variables are used in upper tiers for validation purposes as sending messages to the user, also for committing o rolling back transactions.
Perhaps i'm missing important features like RAISERROR or not cosidering better and more optimal and secure approaches.
I would appreciate your advices and good practices, not asking for cooks recipes there's no need, just the idea but if you decide to include examples they'd be more than welcome.
Thanks
The generally accepted approach for dealing with this is to have your sproc set a return values
and use raise error as has been previously suggested.
The key thing that I suspect you are missing is how to get this data back on the client side.
If you are in a .net environment, you can check for the return value as part of the ado.net code. The raise error messages can be captured by catching the SqlException object and iterating through the errors collection.
Alternatively, you could create and event handler and attach to the connection InfoMessage event. This would allow you to get the messages as they are generated from sql server instead of at the completion of the batch or stored procedure.
another option which I wouldn't recommend, would be to track all of the things you care about into a XML message and return that from the stored proc this gives you a little more structure then your free text field approach.
My experience has been to rely on the inherent workings of the procedure mechanisms. What I mean by this is that if a procedure is to fail, either the implicit raised error (if not using try/catch . . . simply CRUD stuff) or using the explicit RAISERROR. This means that if the code falls into the catch block and I want to notify the application of the error, I would re-raise the error with RAISERROR. In the past, I've have created a custom rethrow procedure so I can trap and log the error information. One could use the rethrow as an opportunity to throw a custom message/code that could be used to guide the application down a different decision path. If the calling application doesn't receive an error on execution, it's safe to assume that it succeeded - so explicit transaction committing can commence.
I've never attempted to write in my own communication mechanism for interaction between the app and the stored proc - the objects in the languages I interact with have events or mechanisms to detect the raised error from the procedure. It sounds to me like your approach doesn't necessarily require too much more code than standard error handling, but I do find it confusing as it seems to be a reinventing the wheel type of scenario.
I hope I've not misunderstood what you are doing, nor do I want to come off as critical; I do believe, however, you have this feedback mechanism available with the standard API and are probably making this too complicated. I would recommend reading up on RAISERROR and see if it's going to meet your needs (see the Using RAISERROR link for this at the bottom of the page as well).