I run < 24 checks on my systems. Servers are not regularly heavily loaded. Load averages keep well under 1 during normal operation.
I have noticed a re-occurring issue where the check-cpu check would start triggering high load averages on systems where there was no organic cause for high load. Further investigation showed the high load report was actually due to the check-cpu script running in parallel with other checks. Outside of the checks executing, cpu load was fine.
I upgraded from sensu 0.20 to 0.23 and continued to observe the same issue.
We found that a re-start of the sensu-server and sensu-client services would resolve the problem for a period of time (approximately 24 hours) and then it would return.
We theorized at this point, there must be some sort of time-delay in the dispatch / execution of the checks on the host which causes this overlap to eventually occur.
All checks are set to run at an interval of 30 or 60.
I decided to set the interval of the check-cpu check to 83, and the issue has not occurred since. Presumably because the check-cpu check does not coincide with any others, thus not seeing high cpu load during that short moment.
Is this some sort of inherent scheduling issue with sensu? Is it supposed to know how to dispatch checks with adequate spacing, or is this something that should be controlled by the interval parameter?
Thanks!

I have noticed that the checks drift in execution time. i.e they do not run exactly every 30 seconds but every 30.001s or something like that. I guess the drift might be different on different checks. So eventually you will run into the problem that the checks sync up and all run at the same time, causing the problem. Running more checks at regular intervals (30s, 60s etc) will make this problem occur more often. If you want a change to this problem you have to report it to sensu directly. I think they might fix it eventually since they probably want the system to be scalable.

Related

Is it possible to accelerate time in grafana?

Actually what I want to do,
I created dashboards to monitor the alert status in grafana.
I created fake data in my system to simulate my alert situations on these boards. The time of this data covers the range now - now + 12h. In fact, it takes a long time to analyze the alert status in real data. For this reason, I cannot be very flexible on my alert rules. I have to wait until the end of this period to see alert status in the system. (I have many states like this actually.) Grafana creates pending, alerting, and ok states according to the records in my database. Is there a method to quickly verify my tests without waiting for this time?
The main problem is that it is fairly expensive to do in a data source agnostic way. The way worked in Bosun is you would select a time range, and then an interval or a number of queries to run.
Setting both From and To enables testing multiple iterations of the selected alert over time. The number of iterations depends on the setting to the two linked fields Intervals and Step Duration at 3 Changing one changes the other. Intervals will be the number of runs to do even spaced out over the duration of From to To and Step Duration is how much time in minutes should be between intervals. Doing a test over time will populate the Timeline tab 5 which draws a clickable graphic of severity states for each item in the set:
It would then run all those queries with a pool limiting simultaneous queries. For an interval of say 5 minutes, it would run adjacent 5 minute queries.
So this would speed up the alert authoring and testing workflow significantly. But it would best be implemented as a job system. This is because with more expensive queries, or range/interval combination that is a fair amount of runs, it may take a minute or so - so having to wait on an open network connection is less ideal.
So I found I generally used in two modes:
To tweak a specific alert that had fired at some time
To get a general overview of how much the alert rule would trigger for the historical data
For the general over, a larger time range is generally wanted, which means more queries if the interval is kept the same. And with a feature like FOR (Pending), you would have to use the same interval it would actually run at.
So possible, has some limitations, and some care needs to be taken to do it right. But extremely useful in my experience.

Does the Overpas API installation's Area Creation process resume if stopped/started?

The Area Creation process can take up to 24 hours. If something happens during that time which causes the process to stop, will it resume when I run it again or does it start back over from the beginning?
We can assume for this question that the files in $DB_DIR remain in place throughout the running/stopping/starting process.
It will start over from the beginning, assuming you're using areas.osm3s to define the area creation rules. This file contains a number of queries which are being executed to generate the areas. If you restart the process, it will execute those very same queries again from the beginning.
For performance reasons, we use areas_delta.osm3s and the accompanying rules_delta_loop.sh script on the production servers. This way, we can limit the workload to those areas, which have been changed since the last area creation run.

Can a process ask for x amount of time but take y amount instead?

If I am running a set of processes and they all want these burst times: 3, 5, 2 respectively, with the total expected time of execution being 10 time units.
Is it possible for one of the processes to take up more that what they ask for? For example even though it asked for 3 it took 11 instead because it was waiting on the user to enter some input. So the total execution time turns out to be 18.
This was all done in a non-preemptive cpu scheduler.
The reality is that software has no idea how long anything will take - my CPU runs at a different "nominal speed" to your CPU, both our CPUs keep changing their speed for power management reasons, and the speed of software executed by both our CPUs is effected by things like what other CPUs are doing (especially for SMT/hyper-threading) and what other devices happen to be doing at the time (their effect on caches, shared RAM bandwidth, etc); and software can't predict the future (e.g. guess when an IRQ will occur and take some time and upset the cache contents, guess when a read from memory will take 10 times longer because there was a single bit error that ECC needed to correct, guess when the CPU will get hot and reduce its speed to avoid melting, etc). It is possible to record things like "start time, burst time and end time" as it happens (to generate historical data from the past that can be analysed) but typically these things are only seen in fabricated academic exercises that have nothing to do with reality.
Note: I'm not saying fabricated academic exercises are bad - it's a useful tool to help learn basic theory before moving on to more advanced (and more realistic) theory.
Instead; for a non-preemptive scheduler, tasks don't try to tell the scheduler how much time they think they might take - the task can't know this information and the scheduler can't do anything with that information (e.g. a non-preemptive scheduler can't preempt the task when it takes longer than it guessed it might take). For a non-preemptive scheduler; a task simply runs until it calls a kernel function that waits for something (e.g. read() that waits for data from disk or network, sleep() that waits for time to pass, etc) and when that happens the kernel function that was called ends up telling the scheduler that the task is waiting and doesn't need the CPU, and the scheduler finds a different task to run that can use the CPU; and if the task never calls a kernel function that waits for something then the task runs "forever".
Of course "the task runs forever" can be bad (not just for malicious code that deliberately hogs all CPU time as a denial of service attack, but also for normal tasks that have bugs), which is why (almost?) nobody uses non-preemptive schedulers. For example; if one (lower priority) task is doing a lot of heavy processing (e.g. spending hours generating a photo-realistic picture using ray tracing techniques) and another (higher priority) task stops waiting (e.g. because it was waiting for the user to press a key and the user did press a key) then you want the higher priority task to preempt the lower priority task "immediately" (e.g. because most users don't like it when it takes hours for software to respond to their actions).

why a update-period value for kubernetes rolling-update should be long (default: 1m0s)?

I was wondering what would be the potential problem if I reduce the --update-period (whose default value is 1m0s) to about 5s (or even 1s)? I've watched a few video clips, and it seems the presenters implied that it's a bad idea to have a short period but did not explain why.
The reason why I want to make it shorter is that we sometimes prefer fast and a little risky transition, rather than safe and steady one. As far as I know, what rolling-update does is:
while the goal has not been achieved {
scale-up the new version
sleep as specified by --update-period
scale-down the old one
check deadline
}
From the above flow, I don't see any problem of not sleeping for a long time. Deadline checking is based on the timeout configuration, and so, it seems the only outcome of changing the --update-period would be iterating the loop more frequently.
One thing I have not fully understood is how scaling down is performed, but I assume that it still does graceful termination, such as sending SIGTERM and waiting for 30s until finally sending SIGKILL to the processes in the pod.
FYI, I'm using the Google Container Engine.
It should not be long, this is just a precaution in case a pod transitions to a Running state but crashes a couple of seconds later. If your update period is short, you'll keep deploying pods that are unstable eventually, and won't give the whole process enough time to notice.
If you're willing to take the risk it's totally fine to have a short update period.
Also, if you want true fast and reliable deployments you should check the Deployment API. The rolling update logic happens server side which increases the reliability and speed.

Work around celerybeat being a single point of failure

I'm looking for recommended solution to work around celerybeat being a single point of failure for celery/rabbitmq deployment. I didn't find anything that made sense so far, by searching the web.
In my case, once a day timed scheduler kicks off a series of jobs that could run for half a day or longer. Since there can only be one celerybeat instance, if something happens to it or the server that it's running on, critical jobs will not be run.
I'm hoping there is already a working solution for this, as I can't be the only one who needs reliable (clustered or the like) scheduler. I don't want to resort to some sort of database-backed scheduler, if I don't have to.
There is an open issue in celery github repo about this. Don't know if they are working on it though.
As a workaround you could add a lock for tasks so that only 1 instance of specific PeriodicTask will run at a time.
Something like:
if not cache.add('My-unique-lock-name', True, timeout=lock_timeout):
return
Figuring out lock timeout is well, tricky. We're using 0.9 * task run_every seconds if different celerybeats will try to run them at different times.
0.9 just to leave some margin (e.g. when celery is a little behind schedule once, then it is on schedule which would cause lock to still be active).
Then you can use celerybeat instance on all machines. Each task will be queued for every celerybeat instance but only one task of them will finish the run.
Tasks will still respect run_every this way - worst case scenario: tasks will run at 0.9*run_every speed.
One issue with this case: if tasks were queued but not processed at scheduled time (for example because queue processors was unavailable) - then lock may be placed at wrong time causing possibly 1 next task to simply not run. To go around this you would need some kind of detection mechanism whether task is more or less on time.
Still, this shouldn't be a common situation when using in production.
Another solution is to subclass celerybeat Scheduler and override its tick method. Then for every tick add a lock before processing tasks. This makes sure that only celerybeats with same periodic tasks won't queue same tasks multiple times. Only one celerybeat for each tick (one who wins the race condition) will queue tasks. In one celerybeat goes down, with next tick another one will win the race.
This of course can be used in combination with the first solution.
Of course for this to work cache backend needs to be replicated and/or shared for all of servers.
It's an old question but I hope it helps anyone.