Differentiate the different area paths in Azure Boards under the same Team - azure-devops

At the moment, I have one Team with two different area paths defined, however I have issues filtering out the epics and features that are related to one of the area paths since the Filter option does not keep the tree form in its result.
Is there a better way to organize the backlog when I have two different area paths and need easily identify which one a work item belongs to?

Is there a better way to organize the backlog when I have two different area paths and need easily identify which one a work item belongs to?
Method 1. Add "Area Path" as a Column.
Click Column Options at the top and Add "Area Path" as a clumn. Then you can see area directly at the page.
Method 2. Use queries.
Go to Boards/Queries. Create a query and set your Work Item Type and your Area path. Here is an example.
Then select "Tree of work items" in "Type of query".
You will find work items in a specific area arranged in a tree form.

One way to filter is by specifying an area path in the filter text area like:
Note that it does not work with the Kanban board.

Related

Is there a way to filter an Azure DevOps board using dates?

On the Boards section of Azure DevOps, there's a nice filter bar. It contains filters for:
Type
Assigned to
Tags
Iteration
Area
Parent work item
As far as I can see, there's no way to use the section outlined in yellow to filter for work items (for example) created within the last seven days, or due within the next 14 days.
Things I've tried:
Creating a query and viewing results as a board (can't see an option to do that)
Finding a way to script work items into iterations based on date, and then filtering the board based on iteration
Is there a way to do this? It's specifically a board I'd like, as opposed to a Backlog-style list.
Just change the board's settings, Is this what you want?

Where is the overview of all work items (across all boards)

When, in Azure Devops, opening the Boards > Backlog page there is no possibility to have an overview of all work items accross all of the teams.
You see "All backlogs", but they are divided into the teams.
I want to see an overview of all work items for all these teams.
Is this possible?
You can just create a simple query:
Then you can format it as a flat list or tree.
But keep in mind that the limit for query results is 20000 items.
I want to see an overview of all work items for all these teams.
You can't do that using any of the regular azure boards (kanban board and sprint board).
The only way (well, the only way known to me) to do that is with Queries (Boards -> Queries). To see work items across projects, remember to check the Query across projects checkbox.
At your disposal you have myriads of fields that you can use to filter your results as well. Use them to fine tune your query result if you want. Last but not least, use Column options to specify which columns to show in your result. Since you want work items across projects, you may want to be able to see which project an item belongs to without opening the item. To do that, include the column Area path from Column options dialog. I use the following columns, and sort by ID descending.
Finally save the query.
Now go to Dashboard, click the Edit button, and add the Query Results widget. Configure that widget to use the query you just created. Note that by default, the column Area Path is not included in the Selected columns list on the right, but you have to include it yourself from the Available columns list on the left. Move columns up/down as you see fit.
Click Done editing when you are done. Through that widget you can edit the work items by clicking on the Title of each work item, which will open the item in a modal. You cannot reorder items (I suppose to set priority) on this widget itself, but hey, setting priority is just a few clicks away, so not a big deal. If you like, you can sort the query result using Priority, and after updating priority you should click Refresh to see the updated result.
Hope that helps!

How to add an existing work item to a board?

How do I add an existing work item to a the default board?
I can create work items under the Work Items section and I can also create work items by clicking + New Item in the Boards section.
But how can I add an existing item to that board?
I cannot find a setting, field, option anywhere to do that.
This is an organization Azure DevOps.
Your existing item needs to be "visible" to the board by existing in the appropriate iteration path and area path.
Without breaking out all the organization settings that allow you to detail this stuff, the easy way to know the value you need to use is to create a new item on the board you want, and use the values it gets in iteration path and area path on the existing item.
Illustrations:
Make sure your project has areas and iterations that make sense for you. Typically your project will start out with a root iteration path and three child iteration paths:
Iteration 1
Iteration 2
Iteration 3
Iteration paths are used to handle both backlogs and sprints for teams.
The combination of area path and iteration path allows admins to divide sections of the global backlog among the teams that are doing the work.
Think of the connection like a grid. If the rows are iteration paths, then the areas are the columns that divide that row (or vise versa). Multiple teams can operate on the same row (iteration/backlog), but they will only see the work items that also fall inside their assigned columns (areas).
When you create a team the area can be created for you, or you can assign an area to a team after it is created.
You can also change the backlog iteration for a team.
Now your team has a board and a backlog. Again, for your first team, this is done for you.
You have obviously already created some work items, so you'll need to move them into the right area and iteration to make them show up.
This can also be done in bulk from another team backlog
You can configure the board on what to be displayed.
By default, it's the Backlog items, so you will see the work items from your backlog (according to the sprints).
You can't just add a particular work item to the board.
See more details here.

Tableau: how to build cascading parameters?

Just see as following image
what I want to realize is, when I choose a specific area in the Area dropbox, The Block dropbox only shows the content which only belong to the selected area. How to realize that in tableau? Area and Block are both parameters.
I would advice you to use filter. then for the block filter,click the arrow on the top right and select "Only Relevant Values".The block filter will then refresh after you choose an area to show only the blocks related to that area.
For parameters currently the dynamic refresh feature is not present, though it is being demanded.
Filters can cascade in Tableau if you select the "Relevant Values" option on the quick filter. (see the little black triangle in the top right of the quick filter).
You may want to also put the two fields into a hierarchy to teach Tableau that Blocks are subordinate to Areas, but Tableau will try to show only relevant values even if you don't define the hierarchies explicitly. To make a hierarchy, drag fields on top of each other in the data pane on the left.
There is no concept of relevant values for parameters currently. Each has an independent range of values. Parameters are not tied to a data source.

SSRS Multiple parameters in single drop-down

I have a feeling I am probably out of luck on this one, but Is it possible to have more than one parameter in a single drop-down list on an SSRS report? For example, the drop-down could be titled shape/color, and when opened, the top of the list shows shapes, and one can be checked, then below that in the same list, is a list of colors, where one can also be checked. Possible at all?
It is really best to have separate drop-downs for each attribute, but within a single drop-down you would first set it to "Allow multiple values". You can setup your drop-down to be formatted so that the sections of available values are grouped together. Finally, you'll need to add a query or function to check that valid combinations were selected before trying to display the results. In other words, make sure only one shape was selected. You can set an error message with a visibility that toggles based on the selection. This is one method to do what you are looking for, but if you are new to SSRS, you will probably have more specific questions along the way. Once you have more details on a specific step, you can get help with that.